Question
You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?
Options
- A-75 percent to +75 percent
- B-25 percent to +25 percent
- C-50 percent to +50 percent
- D-50 percent to +100 percent