You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?

The correct answer is D. -50 percent to +100 percent. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?

Options

  • A-75 percent to +75 percent
  • B-25 percent to +25 percent
  • C-50 percent to +50 percent
  • D-50 percent to +100 percent

How the community answered

(41 responses)
  • A
    7% (3)
  • B
    12% (5)
  • C
    2% (1)
  • D
    78% (32)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#rough order of magnitude#estimation accuracy#initiation phase#cost estimating