ISEB-PM1 · Question #618
ISEB ISEB-PM1 Exam In crashing a task, you would focus on:
The correct answer is D. Accelerating performance of tasks on critical path. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
ISEB ISEB-PM1 Exam In crashing a task, you would focus on:
Options
- AAccelerate performance by minimizing cost.
- BAs many tasks as possible and accelerate performance by minimizing cost.
- CNon critical tasks.
- DAccelerating performance of tasks on critical path.
- EAs many tasks as possible.
How the community answered
(42 responses)- A14% (6)
- B2% (1)
- C2% (1)
- D76% (32)
- E5% (2)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#crashing#critical path#schedule compression#cost-time tradeoff