ISEB ISEB-PM1 Exam Overlapping activities on a project, such as design and construction, is referred to as:
The correct answer is C. Fast tracking. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
ISEB ISEB-PM1 Exam Overlapping activities on a project, such as design and construction, is referred to as:
Options
- AProcess improvement.
- BSynchronous manufacturing
- CFast tracking
- DParallel management.
- ERisk conversion.
How the community answered
(48 responses)- A4% (2)
- B2% (1)
- C71% (34)
- D8% (4)
- E15% (7)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#fast tracking#schedule compression#overlapping activities#schedule management