nerdexam
BCS-ISEB

ISEB-PM1 · Question #603

The estimated cost to complete (ETC) is _____.

The correct answer is B. the forecasted and final cost - cost to date. You've hit your weekly limit · resets 5am (America/New_York)

Project Control

Question

The estimated cost to complete (ETC) is _____.

Options

  • ABCWP/ACWP
  • Bthe forecasted and final cost - cost to date
  • CNone of the other alternatives apply.
  • DTotal estimate - ACWP
  • E(ACWP-BCWP)/BCWP * 100

How the community answered

(32 responses)
  • A
    16% (5)
  • B
    72% (23)
  • C
    3% (1)
  • D
    3% (1)
  • E
    6% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#earned value management#estimate to complete#ETC#cost forecasting

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice