BCS-ISEB
ISEB-PM1 · Question #603
The estimated cost to complete (ETC) is _____.
The correct answer is B. the forecasted and final cost - cost to date. You've hit your weekly limit · resets 5am (America/New_York)
Project Control
Question
The estimated cost to complete (ETC) is _____.
Options
- ABCWP/ACWP
- Bthe forecasted and final cost - cost to date
- CNone of the other alternatives apply.
- DTotal estimate - ACWP
- E(ACWP-BCWP)/BCWP * 100
How the community answered
(32 responses)- A16% (5)
- B72% (23)
- C3% (1)
- D3% (1)
- E6% (2)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#earned value management#estimate to complete#ETC#cost forecasting
Community Discussion
No community discussion yet for this question.