BCS-ISEB
ISEB-PM1 · Question #595
ISEB-PM1 Question #595: Real Exam Question with Answer & Explanation
Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #595. The question stem and answer options stay visible for context.
Question
Sally is a project manager working on a project that will require a specially engineered machine. Only three manufacturers can make the machine to the specifications Sally needs. The price of this machine is particularly critical to this project. The budget is limited, and there's no chance of securing additional funds if the bids for the machine come in higher than budgeted. She's developing the evaluation criteria for the bidders' responses and knows all of the following are true except for which one?
Options
- ASally will review the project management plan, including the risk register, as inputs to this
- BSally will base the evaluation criteria on price alone since the budget is a constraint.
- CSally will update the contract statement of work with any new information.
- DSally will use standard contract forms provided by her procurement department to write the
Unlock ISEB-PM1 to see the answer
You've previewed enough free ISEB-PM1 questions. Unlock ISEB-PM1 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.