Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you worked on last year. She would like to get the cost…

The correct answer is B. analogous estimating techniques. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide to use ___________________.

Options

  • Aparametric modeling techniques
  • Banalogous estimating techniques
  • Cbottom-up estimating techniques
  • Dcomputerized modeling techniques

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    70% (19)
  • C
    19% (5)
  • D
    7% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#analogous estimating#cost estimation#ballpark estimate#historical information

Community Discussion

No community discussion yet for this question.