Your company, Kick That Ball Sports, has appointed you project manager for its new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to…

The correct answer is C. The WBS encompasses the full scope of work for the project and the technique in the question. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

Your company, Kick That Ball Sports, has appointed you project manager for its new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, two of which will be introduced together and a third one that will follow within two years. Product number three will be elaborated in more detail closer to the product's release date, while the first two products will be elaborated in great detail now. The scope management plan has just been completed. Which of the following is true? (Choose the best response.)

Options

  • AThe WBS template from a previous project, a tool and technique of the Create WBS process,
  • BOnly the deliverables associated with the work of the project should be listed on the WBS.
  • CThe WBS encompasses the full scope of work for the project and the technique in the question
  • DThe WBS should be created next, and it encompasses the full scope of work for the project.

How the community answered

(53 responses)
  • A
    17% (9)
  • B
    8% (4)
  • C
    72% (38)
  • D
    4% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#WBS#scope management#rolling wave planning#work breakdown structure