Question

The critical path in a schedule network is the path that:

Options

  • ATakes the longest time to complete
  • BAllows some flexibility in scheduling a start time.
  • CIs not affected by schedule slippage
  • DMust be done before any other tasks
  • EAll of the other alternatives apply.