The critical path in a schedule network is the path that:

The correct answer is A. Takes the longest time to complete. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

The critical path in a schedule network is the path that:

Options

  • ATakes the longest time to complete
  • BAllows some flexibility in scheduling a start time.
  • CIs not affected by schedule slippage
  • DMust be done before any other tasks
  • EAll of the other alternatives apply.

How the community answered

(39 responses)
  • A
    74% (29)
  • B
    3% (1)
  • C
    13% (5)
  • D
    8% (3)
  • E
    3% (1)

Explanation