The critical path in a schedule network is the path that:
The correct answer is A. Takes the longest time to complete. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
The critical path in a schedule network is the path that:
Options
- ATakes the longest time to complete
- BAllows some flexibility in scheduling a start time.
- CIs not affected by schedule slippage
- DMust be done before any other tasks
- EAll of the other alternatives apply.
How the community answered
(39 responses)- A74% (29)
- B3% (1)
- C13% (5)
- D8% (3)
- E3% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#critical path#network diagram#schedule analysis#float