nerdexam
BCS-ISEB

ISEB-PM1 · Question #432

Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships. What is the critical path…

The correct answer is D. 25. Option D (25) is correct because the critical path is the longest path through the network - it represents the minimum time to complete the project. By summing activity durations along every path from start to finish using Finish-to-Start (F-S) relationships in the AON diagram…

Project Planning

Question

Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships. What is the critical path duration for the given schedule network?

Options

  • A22
  • B23
  • C24
  • D25

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    15% (6)
  • D
    74% (29)

Explanation

Option D (25) is correct because the critical path is the longest path through the network - it represents the minimum time to complete the project. By summing activity durations along every path from start to finish using Finish-to-Start (F-S) relationships in the AON diagram, the longest continuous sequence of activities totals 25 time units, which drives the project end date.

Options A (22), B (23), and C (24) are wrong because they represent shorter paths through the network - near-critical or non-critical paths that have float/slack. Choosing the shortest or middle path is a common trap; the critical path is never the fastest route, it's the longest.

Memory tip: Think of the critical path as the "bottleneck chain" - like the longest line at an amusement park. No matter how fast the other lines move, you can't leave until the longest line clears. CP = Longest Path = Project Duration.

Topics

#critical path duration#AON network diagram#finish-to-start#schedule calculation

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice