nerdexam
BCS-ISEB

ISEB-PM1 · Question #423

ISEB-PM1 Question #423: Real Exam Question with Answer & Explanation

Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #423. The question stem and answer options stay visible for context.

Question

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options

  • A90 days
  • B100 days
  • C110 days
  • D660 days

Unlock ISEB-PM1 to see the answer

You've previewed enough free ISEB-PM1 questions. Unlock ISEB-PM1 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full ISEB-PM1 Practice