nerdexam
BCS-ISEB

ISEB-PM1 · Question #423

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is…

The correct answer is C. 110 days. ISEB ISEB-PM1 Exam

Project Planning

Question

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options

  • A90 days
  • B100 days
  • C110 days
  • D660 days

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    19% (6)
  • C
    72% (23)
  • D
    6% (2)

Explanation

ISEB ISEB-PM1 Exam

Topics

#three-point estimating#PERT formula#activity duration#beta distribution

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice