Project Planning
Question
In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?
Options
- A90 days
- B100 days
- C110 days
- D660 days
How the community answered
(32 responses)- A3% (1)
- B19% (6)
- C72% (23)
- D6% (2)
Explanation
ISEB ISEB-PM1 Exam
Topics
#three-point estimating#PERT formula#activity duration#beta distribution