ISEB-PM1 · Question #421
Which is the total float for the activity G?
The correct answer is C. 5. Total float is calculated as Late Start minus Early Start (LS − ES) or equivalently Late Finish minus Early Finish (LF − EF). For activity G, the values from the network diagram yield a difference of 5, meaning G can be delayed up to 5 time units without pushing back the…
Question
Which is the total float for the activity G?
Options
- A0
- B3
- C5
- D10
How the community answered
(52 responses)- A12% (6)
- B6% (3)
- C79% (41)
- D4% (2)
Explanation
Total float is calculated as Late Start minus Early Start (LS − ES) or equivalently Late Finish minus Early Finish (LF − EF). For activity G, the values from the network diagram yield a difference of 5, meaning G can be delayed up to 5 time units without pushing back the project completion date.
Why the distractors are wrong:
- A (0) would mean G is on the critical path with zero slack - but G has scheduling flexibility, so it is not critical.
- B (3) may result from confusing free float (delay before affecting a successor) with total float (delay before affecting the project end), or from a miscalculation of the path durations.
- D (10) overstates the slack and likely comes from using incorrect late/early dates - perhaps reading the wrong node values from the network diagram.
Memory tip: Think of total float as your "project budget" of delay - it's always measured against the project's final deadline, not just the next activity. When in doubt, trace the longest path to the end node; total float = (that path's latest allowable dates) minus (earliest possible dates) for your activity.
Topics
Community Discussion
No community discussion yet for this question.