Which is the duration of the project?
The correct answer is D. 70. See the full explanation below for the reasoning.
Project Planning
Question
Which is the duration of the project?
Options
- A63
- B65
- C66
- D70
How the community answered
(35 responses)- A9% (3)
- B3% (1)
- C6% (2)
- D83% (29)
Topics
#project duration#critical path#network diagram#schedule calculation