ISEB-PM1 · Question #297
How is the process of collecting requirements defined?
The correct answer is B. Defining and documenting stakeholders' needs to meet the project objectives. See the full explanation below for the reasoning.
Project Planning
Question
How is the process of collecting requirements defined?
Options
- ADefining and documenting project sponsors' needs to meet the project objectives
- BDefining and documenting stakeholders' needs to meet the project objectives
- CDefining and documenting the project teams' needs to meet the project objectives
- DDefining and documenting the project needs to meet the project objectives
How the community answered
(31 responses)- A13% (4)
- B81% (25)
- C3% (1)
- D3% (1)
Topics
#requirements collection#stakeholder needs#scope planning#requirements definition