ISEB-PM1 · Question #297

How is the process of collecting requirements defined?

The correct answer is B. Defining and documenting stakeholders' needs to meet the project objectives. See the full explanation below for the reasoning.

Project Planning

Question

How is the process of collecting requirements defined?

Options

  • ADefining and documenting project sponsors' needs to meet the project objectives
  • BDefining and documenting stakeholders' needs to meet the project objectives
  • CDefining and documenting the project teams' needs to meet the project objectives
  • DDefining and documenting the project needs to meet the project objectives

How the community answered

(31 responses)
  • A
    13% (4)
  • B
    81% (25)
  • C
    3% (1)
  • D
    3% (1)

Topics

#requirements collection#stakeholder needs#scope planning#requirements definition

Community Discussion

No community discussion yet for this question.