nerdexam
BCS-ISEB

ISEB-PM1 · Question #267

Project contracts generally fall into which of the following three broad categories?

The correct answer is A. Fixed-price, cost reimbursable, time and materials. Option A is correct because project management frameworks (including PMI/PMBOK) recognize fixed-price, cost-reimbursable, and time & materials as the three fundamental contract categories - each representing a different way of allocating cost risk between buyer and seller. Why…

Project Planning

Question

Project contracts generally fall into which of the following three broad categories?

Options

  • AFixed-price, cost reimbursable, time and materials
  • BMake-or-buy, margin analysis, fixed-price
  • CTime and materials, fixed-price, margin analysis
  • DMake-or-buy, lump-sum, cost-plus-incentive

How the community answered

(48 responses)
  • A
    83% (40)
  • B
    6% (3)
  • C
    2% (1)
  • D
    8% (4)

Explanation

Option A is correct because project management frameworks (including PMI/PMBOK) recognize fixed-price, cost-reimbursable, and time & materials as the three fundamental contract categories - each representing a different way of allocating cost risk between buyer and seller.

Why the distractors are wrong:

  • B mixes in "make-or-buy" (a procurement decision, not a contract type) and "margin analysis" (a financial evaluation technique, not a contract category).
  • C replaces cost-reimbursable with "margin analysis," which again is an analytical tool, not a contract form.
  • D includes "make-or-buy" and "lump-sum" - lump-sum is actually a subtype of fixed-price, not a separate top-level category, and make-or-buy is still a decision framework.

Memory tip: Think FCT - Fixed, Cost-reimbursable, T&M. These map to how risk is distributed: Fixed = seller bears cost risk, Cost-reimbursable = buyer bears it, T&M = shared. Any answer mixing in "make-or-buy" or "margin analysis" is pulling from a different topic entirely and can be eliminated immediately.

Topics

#contract types#fixed-price#cost reimbursable#time and materials

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice