ISEB-PM1 · Question #249
Cost baseline is an output of which of the following processes? ISEB ISEB-PM1 Exam
The correct answer is B. Cost Budgeting. Cost Budgeting produces the cost baseline because it's the process that aggregates estimated costs for individual activities or work packages and establishes the time-phased budget that serves as the reference point for measuring project performance. Why the distractors are…
Question
Cost baseline is an output of which of the following processes? ISEB ISEB-PM1 Exam
Options
- ACost Control
- BCost Budgeting
- CCost Estimating
- DCost Planning
How the community answered
(19 responses)- A5% (1)
- B74% (14)
- C5% (1)
- D16% (3)
Explanation
Cost Budgeting produces the cost baseline because it's the process that aggregates estimated costs for individual activities or work packages and establishes the time-phased budget that serves as the reference point for measuring project performance.
Why the distractors are wrong:
- A. Cost Control - This process uses the cost baseline to monitor and manage variances; it doesn't create it.
- C. Cost Estimating - This produces cost estimates (approximations of resource costs), which are inputs into Cost Budgeting, not the baseline itself.
- D. Cost Planning - "Cost Planning" is not a standard PMBOK process name; it's a distractor designed to sound plausible.
Memory tip: Think of it as a pipeline - Estimate → Budget → Baseline. Cost Estimating gives you numbers; Cost Budgeting Bakes them into a Baseline. The three B's lock it in.