ISEB-PM1 · Question #198

Which may be employed to shorten a schedule without changing the scope of the task?

The correct answer is D. Fast tracking. Fast tracking is the only technique that compresses a schedule purely by overlapping sequential tasks - starting a downstream task before its predecessor finishes - without altering what the task delivers or how resources are allocated. It changes when work happens, not what or…

Project Planning

Question

Which may be employed to shorten a schedule without changing the scope of the task?

Options

  • AAlter to task priorities.
  • BReleasing resources earlier from tasks which were scheduled with a late start.
  • CFast tracking or Crashing
  • DFast tracking.
  • ECrashing

How the community answered

(27 responses)
  • B
    4% (1)
  • C
    7% (2)
  • D
    74% (20)
  • E
    15% (4)

Explanation

Fast tracking is the only technique that compresses a schedule purely by overlapping sequential tasks - starting a downstream task before its predecessor finishes - without altering what the task delivers or how resources are allocated. It changes when work happens, not what or with what.

Why the distractors fail:

  • A (Alter task priorities): Changing priorities reorders work but doesn't shorten the overall schedule duration - it just changes what gets done first.
  • B (Releasing resources early from late-start tasks): This reallocates resources but risks leaving those tasks under-resourced; it doesn't reliably compress the schedule without scope or risk implications.
  • C (Fast tracking or Crashing): Crashing adds resources/cost to shorten a task, which effectively changes the execution parameters of the task - many exam frameworks treat this as altering the task's cost baseline, making it a broader change than a pure schedule compression without side effects.
  • E (Crashing): Same issue as above - crashing trades money for time and changes the resource profile of the task, so it's not purely a schedule shortcut "without changing" anything about the task.

Memory tip: Think of fast tracking as a racing driver cutting corners - the destination (scope) doesn't change, you just find a shorter path. Crashing is like buying a faster car - you're changing something material about the execution itself.

Topics

#fast tracking#schedule compression#schedule shortening#scope preservation