Question
Which of the following would most likely increase the accuracy of estimating the project cost?
Options
- AUsing historical data.
- BPricing out the work at lower levels in the work breakdown structure.
- CBoth 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to
- DTalking to people who have worked on similar projects.
- E
- Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to