Which of the following is not a cost of non-conformance?
The correct answer is A. maintenance and calibration. You've hit your session limit · resets 10:20pm (America/New_York)
Quality Management
Question
Which of the following is not a cost of non-conformance?
Options
- Amaintenance and calibration
- Bwarranty repairs
- CAll of the other alternatives apply.
- Dscrap
- Erework
How the community answered
(21 responses)- A71% (15)
- B10% (2)
- D5% (1)
- E14% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#cost of quality#cost of non-conformance#conformance costs#quality costs