ISEB-PM1 · Question #157

In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

The correct answer is C. firm fixed price. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

Options

  • Acost plus incentive fee
  • BCost plus incentive fee and firm fixed price
  • Cfirm fixed price
  • Dcost plus fixed fee
  • Eunit price

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    74% (29)
  • D
    5% (2)
  • E
    15% (6)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#contract types#firm fixed price#cost control#procurement