The correct answer is A. customer. See the full explanation below for the reasoning.

Question

You are working with XYZ organization. Your senior manager imposed new delivery date which is earlier than mentioned project deliverables date in scope statement. To whom you are most accountable? ISEB ISEB-PM1 Exam

Options

  • Acustomer
  • Bteam member
  • Csponsor
  • Dsenior manager