Which of the following are inputs of the Perform Quality Control process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Project management plan B. Quality metrics C. Quality checklists. See the full explanation below for the reasoning.
Question
Which of the following are inputs of the Perform Quality Control process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AProject management plan
- BQuality metrics
- CQuality checklists
- DValidated changes
How the community answered
(61 responses)- A84% (51)
- D16% (10)