GIAC
GCPM · Question #178
Which of the following are inputs of the Direct and Manage Project Execution process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Organizational process assets B. Approved change requests D. Project management plan. See the full explanation below for the reasoning.
Question
Which of the following are inputs of the Direct and Manage Project Execution process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AOrganizational process assets
- BApproved change requests
- CQuality metrics
- DProject management plan
How the community answered
(39 responses)- A72% (28)
- C28% (11)
Community Discussion
No community discussion yet for this question.