nerdexam
GIAC

GCPM · Question #290

Wanda is the project manager for her organization and is creating a checklist for her project team. In this project the team will be installing electrical fixtures throughout an office building and sh

The correct answer is C. Quality control. See the full explanation below for the reasoning.

Question

Wanda is the project manager for her organization and is creating a checklist for her project team. In this project the team will be installing electrical fixtures throughout an office building and she wants to confirm that the installations will be done correctly each time. Her goal is that the project deliverables will be of quality throughout the project installation process. In what project process will Wanda's team use the checklist?

Options

  • APlanning quality
  • BProject execution
  • CQuality control
  • DQuality assurance

How the community answered

(35 responses)
  • A
    14% (5)
  • B
    9% (3)
  • C
    74% (26)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice