$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?
The correct answer is D. The project is eight percent off schedule and has a considerable schedule variance. See the full explanation below for the reasoning.
Question
$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?
Options
- AThe project is performing well.
- BThe project has a planned value of $600,000.
- CThe project is likely to be late and over budget.
- DThe project is eight percent off schedule and has a considerable schedule variance.
How the community answered
(39 responses)- A5% (2)
- B8% (3)
- C13% (5)
- D74% (29)