nerdexam
GIAC

GCPM · Question #85

$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?

The correct answer is D. The project is eight percent off schedule and has a considerable schedule variance. See the full explanation below for the reasoning.

Question

$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?

Options

  • AThe project is performing well.
  • BThe project has a planned value of $600,000.
  • CThe project is likely to be late and over budget.
  • DThe project is eight percent off schedule and has a considerable schedule variance.

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    8% (3)
  • C
    13% (5)
  • D
    74% (29)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice