nerdexam
GIAC

GCPM · Question #84

You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine…

The correct answer is C. Transference. See the full explanation below for the reasoning.

Question

You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine the electrical work is too dangerous to perform yourself so you hire an electrician to perform the work for the project. This is an example of what type of risk response?

Options

  • AMitigation
  • BAcceptance
  • CTransference
  • DAvoidance

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    78% (28)
  • D
    11% (4)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice