GCPM · Question #289

GCPM Question #289: Real Exam Question with Answer & Explanation

The correct answer is C. Critical Chain Project Management (CCPM). See the full explanation below for the reasoning.

Question

Which of the following is a method of planning and managing projects that puts more emphasis on the resources required to execute project tasks?

Options

  • ACritical Path Method (CPM)
  • BDynamic Systems Development Method (DSDM)
  • CCritical Chain Project Management (CCPM)
  • DLinear scheduling method (LSM)