The correct answer is A. Face-to-face meeting. See the full explanation below for the reasoning.
Question
You are the project manager of the BGY Project. A new issue has been identified in the project and this issue could prove to be costly for the project. The issue affects Anna's project deliverable and she is a negative stakeholder for the project. Considering these elements of the project, what type of communication would be the most effective to share this news with Anna?
Options
- AFace-to-face meeting
- BDocumented review of the issue
- CImmediate telephone call
- DInformal presentation meeting