You are the project manager of the BGY Project. A new issue has been identified in the project and this issue could prove to be costly for the project. The issue affects Anna's project deliverable…

The correct answer is A. Face-to-face meeting. See the full explanation below for the reasoning.

Question

You are the project manager of the BGY Project. A new issue has been identified in the project and this issue could prove to be costly for the project. The issue affects Anna's project deliverable and she is a negative stakeholder for the project. Considering these elements of the project, what type of communication would be the most effective to share this news with Anna?

Options

  • AFace-to-face meeting
  • BDocumented review of the issue
  • CImmediate telephone call
  • DInformal presentation meeting

How the community answered

(21 responses)
  • A
    81% (17)
  • B
    5% (1)
  • C
    5% (1)
  • D
    10% (2)