Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to…
The correct answer is D. Whomever the communications management plan directs her to. See the full explanation below for the reasoning.
Question
Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?
Options
- AFunctional Management
- BProject customer
- CProject sponsor
- DWhomever the communications management plan directs her to
How the community answered
(18 responses)- A11% (2)
- C6% (1)
- D83% (15)