GCPM · Question #395
Which of the following are inputs of the perform quality assurance process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Project management plan C. Quality metrics D. Work performance information. See the full explanation below for the reasoning.
Question
Which of the following are inputs of the perform quality assurance process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AProject management plan
- BChange requests
- CQuality metrics
- DWork performance information
How the community answered
(55 responses)- A80% (44)
- B20% (11)
Community Discussion
No community discussion yet for this question.