GIAC
GCPM · Question #361
You are the project manager for your organization. Your project is doing fine on time and cost, but management wants to address the project performance for future accomplishment. Management has…
The correct answer is B. Time series methods. See the full explanation below for the reasoning.
Question
You are the project manager for your organization. Your project is doing fine on time and cost, but management wants to address the project performance for future accomplishment. Management has asked you to begin reporting and forecasting your project's health based on a moving average, extrapolation, trend estimation, and growth curve. What type of forecasting method is management asking you to use?
Options
- AEstimate at completion method
- BTime series methods
- CCausal/econometric methods
- DJudgmental methods
How the community answered
(29 responses)- A17% (5)
- B72% (21)
- C7% (2)
- D3% (1)
Community Discussion
No community discussion yet for this question.