Which of the following is described in the statement below? "It is an approved time-phased budget that monitors and measures cost performance throughout the project life cycle."
The correct answer is A. Cost baseline. See the full explanation below for the reasoning.
Question
Which of the following is described in the statement below? "It is an approved time-phased budget that monitors and measures cost performance throughout the project life cycle."
Options
- ACost baseline
- BScope baseline
- CCost budgeting
- DCost estimation
How the community answered
(30 responses)- A77% (23)
- B13% (4)
- C7% (2)
- D3% (1)