project that involves developing a plan for a new building. You have started estimating the activity durations. You find some uncertainty about the estimates due to the nature of the project. This…
The correct answer is A. Three-point estimation. See the full explanation below for the reasoning.
Question
project that involves developing a plan for a new building. You have started estimating the activity durations. You find some uncertainty about the estimates due to the nature of the project. This is your first project. Which of the following estimation techniques is the most likely method that Mark could use to ensure improvement in estimation?
Options
- AThree-point estimation
- BAnalogous estimation
- CHands-down estimation
- DTop-down estimation
How the community answered
(45 responses)- A80% (36)
- B4% (2)
- C11% (5)
- D4% (2)