GCPM · Question #362

GCPM Question #362: Real Exam Question with Answer & Explanation

Sign in or unlock GCPM to reveal the answer and full explanation for question #362. The question stem and answer options stay visible for context.

Question

Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?

Options

  • AAccepting
  • BEnhancing
  • CAvoidance
  • DExploiting

Unlock GCPM to see the answer

You've previewed enough free GCPM questions. Unlock GCPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full GCPM Practice