GCPM · Question #324

projects vary in size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can compare relative schedule and cost performance of each project. Which of the…

The correct answer is B. CPI and SPI. See the full explanation below for the reasoning.

Question

projects vary in size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can compare relative schedule and cost performance of each project. Which of the following components of EVM provide measures of schedule and cost performance that are not affected by the size of the project?

Options

  • ABAC and EAC
  • BCPI and SPI
  • CCV and SV
  • DPV and EV

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    79% (26)
  • C
    3% (1)
  • D
    12% (4)