James works as the project manager for a software project. He and his team are on the Direct and Manage Project Execution process. All of the following are inputs of this process except for which one?
The correct answer is A. Project charter. See the full explanation below for the reasoning.
Question
James works as the project manager for a software project. He and his team are on the Direct and Manage Project Execution process. All of the following are inputs of this process except for which one?
Options
- AProject charter
- BOrganizational process assets
- CEnterprise environmental factors
- DApproved environmental requests
- EProject management plan
How the community answered
(35 responses)- A71% (25)
- B6% (2)
- C17% (6)
- D3% (1)
- E3% (1)