budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost…
The correct answer is C. 0.84. See the full explanation below for the reasoning.
Question
budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?
Options
- A0.87
- B0.80
- C0.84
- D0.86
How the community answered
(40 responses)- A8% (3)
- B18% (7)
- C73% (29)
- D3% (1)