GIAC
GCPM · Question #264
What does CPI value less than 1.0 indicates?
The correct answer is D. Cost overrun for work completed. See the full explanation below for the reasoning.
Question
What does CPI value less than 1.0 indicates?
Options
- ACost underrun of performance to date
- BCost for completed work is as per estimate
- CScheduled performance is great
- DCost overrun for work completed
How the community answered
(39 responses)- A5% (2)
- B13% (5)
- C3% (1)
- D79% (31)
Community Discussion