GCPM · Question #265

Which of the following is a measure of progress achieved compared to progress planned on a project?

The correct answer is B. Schedule performance index. See the full explanation below for the reasoning.

Question

Which of the following is a measure of progress achieved compared to progress planned on a project?

Options

  • ACost variance
  • BSchedule performance index
  • CSchedule variance
  • DCost performance index

How the community answered

(63 responses)
  • A
    6% (4)
  • B
    73% (46)
  • C
    16% (10)
  • D
    5% (3)