GIAC
GCPM · Question #263
Which of the following processes records the results of executing quality activities?
The correct answer is C. Perform quality control. See the full explanation below for the reasoning.
Question
Which of the following processes records the results of executing quality activities?
Options
- AControl risk
- BMonitor risk
- CPerform quality control
- DIdentify risk
How the community answered
(21 responses)- A5% (1)
- B14% (3)
- C76% (16)
- D5% (1)
Community Discussion