Question
Which of the following describes the statement below? "It allocates continuous monitoring of the schedule, permits the project manager to track the critical activities, and alerts the project manager to the possibility that non-critical activities may be delayed beyond their total float, thus creating a new critical path and delaying project completion."
Options
- ACPM
- BRBS
- CGantt chart
- DWBS