GCPM · Question #237

Which of the following techniques is described in the statement below? "It is an early warning project management tool that allows managers to discover and control errors before they become…

The correct answer is B. Earned Value Analysis. See the full explanation below for the reasoning.

Question

Which of the following techniques is described in the statement below? "It is an early warning project management tool that allows managers to discover and control errors before they become unmanageable."

Options

  • AResource leveling
  • BEarned Value Analysis
  • CWhat-if scenario analysis
  • DVariance analysis

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    71% (24)
  • C
    18% (6)
  • D
    6% (2)