budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost…

The correct answer is B. 0.84. See the full explanation below for the reasoning.

Question

budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Options

  • A0.87
  • B0.84
  • C0.86
  • D0.80

How the community answered

(55 responses)
  • A
    7% (4)
  • B
    73% (40)
  • C
    4% (2)
  • D
    16% (9)