GCPM · Question #225
Which of the following is an output of a change control system?
The correct answer is B. Approved changes. See the full explanation below for the reasoning.
Question
Which of the following is an output of a change control system?
Options
- AChange requests
- BApproved changes
- CImpact analysis
- DSignoff
How the community answered
(36 responses)- A14% (5)
- B78% (28)
- C6% (2)
- D3% (1)
Community Discussion
No community discussion yet for this question.