GCPM · Question #226

The company is implementing an enterprise time system across the entire company. This will integrate a number of business units. As a result, it will be very resource-consuming, change a lot of the…

The correct answer is C. What impact the new project is expected to have on your biggest project. See the full explanation below for the reasoning.

Question

The company is implementing an enterprise time system across the entire company. This will integrate a number of business units. As a result, it will be very resource-consuming, change a lot of the business processes and could cause reprioritization of other projects that it will replace or modify. Which of the following would concern you most?

Options

  • AHow many resources you can keep
  • BHow your raise or promotion might be impacted by not being on the project
  • CWhat impact the new project is expected to have on your biggest project
  • DHow many resources you might lose to the new project

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    16% (9)
  • C
    73% (40)
  • D
    7% (4)