All of the following are typically part of the project management plan except?
The correct answer is B. Budget management plan. See the full explanation below for the reasoning.
Question
All of the following are typically part of the project management plan except?
Options
- ASchedule management plan
- BBudget management plan
- CRisk management plan
- DScope management plan
How the community answered
(22 responses)- A5% (1)
- B73% (16)
- C9% (2)
- D14% (3)