GCPM · Question #155

completion time for a project along with the possible start and finish times for the project activities. Which of the following techniques will you use to accomplish the task?

The correct answer is C. Critical path scheduling. See the full explanation below for the reasoning.

Question

completion time for a project along with the possible start and finish times for the project activities. Which of the following techniques will you use to accomplish the task?

Options

  • ATime-oriented scheduling
  • BNetwork scheduling
  • CCritical path scheduling
  • DResource-oriented scheduling

How the community answered

(55 responses)
  • A
    7% (4)
  • B
    13% (7)
  • C
    76% (42)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.