GIAC
GCPM · Question #156
You are using the PDCA model to determine, implement, monitor, control, and maintain Information Security Management System or ISMS. You have to determine where to apply changes that will include…
The correct answer is C. Act. See the full explanation below for the reasoning.
Question
You are using the PDCA model to determine, implement, monitor, control, and maintain Information Security Management System or ISMS. You have to determine where to apply changes that will include improvement. In which of the following phases of PDCA are you working?
Options
- ADo
- BCheck
- CAct
- DPlan
How the community answered
(62 responses)- A8% (5)
- B3% (2)
- C71% (44)
- D18% (11)
Community Discussion
No community discussion yet for this question.