GIAC
GCPM · Question #153
Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk…
The correct answer is B. Mitigation. See the full explanation below for the reasoning.
Question
Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk event to happen so she devises extra project activities to ensure that the risk event will not happen. The extra steps, however, will cost the project an additional $10,000. What type of risk response is this approach?
Options
- ATransference
- BMitigation
- CEnhancing
- DExploiting
How the community answered
(33 responses)- A12% (4)
- B76% (25)
- C3% (1)
- D9% (3)
Community Discussion
No community discussion yet for this question.