The correct answer is D. Integrated change control. See the full explanation below for the reasoning.
Question
You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?
Options
- ASchedule change control
- BScope change control
- CChange Control Board approval process
- DIntegrated change control