GCPM · Question #147
to aggregate the probable costs of individual activities or work packages to set up an authorized cost baseline?
The correct answer is C. Determine Budget. See the full explanation below for the reasoning.
Question
to aggregate the probable costs of individual activities or work packages to set up an authorized cost baseline?
Options
- AEstimate costs
- BControl costs
- CDetermine Budget
- DPlan quality
How the community answered
(24 responses)- A4% (1)
- B4% (1)
- C83% (20)
- D8% (2)