GCPM · Question #147

to aggregate the probable costs of individual activities or work packages to set up an authorized cost baseline?

The correct answer is C. Determine Budget. See the full explanation below for the reasoning.

Question

to aggregate the probable costs of individual activities or work packages to set up an authorized cost baseline?

Options

  • AEstimate costs
  • BControl costs
  • CDetermine Budget
  • DPlan quality

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    83% (20)
  • D
    8% (2)